  • I believe there are six steps to project/task scheduling.
    1. Plan Schedule Management – Define policies, procedures, and documentation
    2. Define Activities – Work Breakdown
    3. Sequence Activities – sequence of work
    4. Estimate Activity Resources – resources such as labor, tools, facilities, fixed cost items
    5. Estimate Activity Duration – estimating the number of work periods
    6. Develop Schedule – develop a schedule to analyze sequences and resource requirements