  • Our capstone team also created a gant chart, and in the beginning it was a lot of guessing on how much time we thought each task would take. We tried to be as accurate as possible by asking the person who would complete the task how much time they thought it would take them. However since the gant chart does not take vacations, spring break, and exam week into consideration, sometimes it was difficult to complete the tasks on time. We did not have any missed milestones due to this, but we had one because of an unexpected error within testing. The 3D piece we used during 3D testing had broke, so we were delayed from completing our testing in time. We had to test very quickly after, and shorten the time span allotted for our next test.