  • sybleb replied to the topic Preplanning for Risk in the forum Project Management Process and Medical Device Development 6 years, 3 months ago

    To minimise the risk of delay, we need to know the finish date and work in the backward direction as studied in the lecture this week. The PM should know how much time each task requires in the process, taking all the factors into consideration i.e sick leave, working hours per day and other necessary factors, we finally knows the project start date and time required for each task. Once we know all this, the risk with the dates will be minimised.