  • ec52 replied to the topic Estimating Project Timeline in the forum Project Management Process and Medical Device Development 6 years, 6 months ago

    This type of scenario was part of the mini-sim this week in which we were asked to deal with delays in timeline which happened due to incorrect task duration. Creation of WBS and task duration is a critical activity that occurs during project initiation. The one key aspect of this activity is to include the actual SMEs (Subject Matter Experts) that will lead the activities and have experience with them to inform the project manager of the appropriate time required for each task. Failure to involve/ consult these SMEs will likely result in an incorrect time schedule which will create churn and stress amongst project team as well as project risks.