You could monitor progress by looking at EV and SV.
Earned Value-the value of the work you have completed so far. Earned Value=Percent complete*original budged cost of task
Schedule Variance (SV)= EV- Planned Value (PV)
If you have a positive SV, that means you are ahead of schedule. If you have a negative value, that means you are behind schedule.