    Unforeseen occurrences are should be factored in with task scheduling. If a schedule is too tight then any delay will cascade into other tasks which depend on the initial task. This will in turn cause those tasks to be delayed, and so forth. In order to help with this task duration should be established with considerations in place in case of any delay that may occur.