Activity

  • For my capstone project, I had to follow a schedule I made on microsoft project. We had allocated a certain amount of time for a specific part of the project. The week before we ran into an issue with whatever we were doing that week and as a result it delayed whatever we were doing the week after. As a result, we had to speed certain things up and work more often on the project to keep up with our schedule. Usually we had like 4-5 hours per week where we would work on the project but because of the issue, we had to 1) fix the issue and 2) do the work that we were delaying. We had to work extra, maybe, 6-7 hours per week now to catch up. We didn’t have a contingency plan because we weren’t really expecting issue with whatever came up so we just had to work overtime to meet the goal.