msc52njit-edu replied to the topic task Scheduling :factors in the forum Project Management Process and Medical Device Development 7 years, 5 months ago
I agree with Monique that those are the necessary 6 steps to the project/task schedule. However, I do believe that other steps should be included. There should be another Risk Analysis step because there could have been a lot of changes that occurred in between processes that could have changed the project. The step should outline what risk are still relevant from the predetermined risks list and what new risk the project had incurred. In addition, the schedule should be devised knowing about what risk could happen in order to develop an accurate time table of the project. I agree with f-dot that there should be an update phase so they can adjust the time line of their project. Also, changes that happen could affect other parts of the project and can affect their time line and efficiency and it is important for all groups and members of the project to communicate so that there are not delays from unknown changes.