RE: Benefits of this course

I could not agree more. I had started interning in industry before taking any of Dr. Simon's classes. I entered not knowing anything about the FDA, GDP or the design control process. Through my experi...

In forum Project Management Process and Medical Device Development

8 years ago
RE: Missing a Milestone Experience

In my senior design course we created a Gantt chart early on and estimated all of the required steps in the critical path. One of which was the procurement of the prototype components. This was a majo...

In forum Project Management Process and Medical Device Development

8 years ago
RE: Revising a Gantt Chart

You make a good point tn58. This will certainly affect the overall project and may require reallocation of time in the preliminary steps of the project schedule. Not only R&D, but other phases suc...

In forum Project Management Process and Medical Device Development

8 years ago
RE: Underestimating Task Duration

More often than not, certain tasks will take longer than estimated and push the project back. This is sometimes unavoidable as there may be many possible bottle necks and obstacles. These can include ...

In forum Project Management Process and Medical Device Development

8 years ago
RE: how the PM handles budget cut?

A budget cut certainly has an effect on cost estimation. I believe generally most projects hope to come under budget or plan ahead to have some wiggle room as more often than not, projects are more co...

In forum Project Management Process and Medical Device Development

8 years ago
RE: Discussion Topic: Design and Process Verification

Shachi, you bring up a good point. However, though it may delay other processes it is essential to, at the very least, carry on project development with verification in mind. Even though the official ...

In forum Project Management Process and Medical Device Development

8 years ago
RE: Discussion Topic: The critical path

I am also working on a capstone project where seemingly minor details have manifested into critical issues that impede the progress of the overall project. This is certainly something that has to be a...

In forum Project Management Process and Medical Device Development

8 years ago
RE: Best timing for validation and verification

The validation and verification steps are extremely important and encompass the overall design control process. Verification ensures that the design outputs adhere to the requirements given in the des...

In forum Introduction to Project Management

8 years ago
RE: Ideal project team

You make a great point Shachi. A team with cross filed knowledge would definitely be advantageous. Often times ideas come from those with different perspectives. In companies where there is little var...

In forum Introduction to Project Management

8 years ago
RE: Simulations

Though there is usually more face to face communication in industry, a great deal gets done via email, phone calls or web chats. This is an essential part as projects can include individuals at other ...

In forum Introduction to Project Management

8 years ago