Which factors should be followed while deciding number of alternative vendors ?

In mini-sim, we had to choose number of alternative vendors. Although it decreases the risk, it also increases cost and time. So, choosing the number of alternative vendors is complicated. Therefore, ...

In forum Project Management Knowledge Areas

1 year ago
RE: Time Management in Medical Devices

I think we can apply some strategies so that we can manage time in the best way. Here, are some strategies that I think should be followed. 1. Planning: There should be a proper plan that describes th...

In forum Project Management Knowledge Areas

1 year ago
RE: Collaborative Research in Academia and Industry

Thank you for the question. I agree with other opinion. However, I want to add some more points. Here are some strategies to foster successful collaborations between academia and industry while safegu...

In forum Project Management Process and Medical Device Development

1 year ago
RE: Monitoring and Controlling in a Project

it's a good question. I agree with others opinion. They mentioned very good points. However, I also want to explain it briefly and give some major points. 1. Quality Assurance: For medical devices, qu...

In forum Project Management Process and Medical Device Development

1 year ago
RE: Verification & Validation NDAs

In my opinion, it is complicated. I agree with others' answers. Since there are both advantages and disadvantages, so certain answer is not feasible. Advantages: 1. Maintaining confidentiality: it ca...

In forum Project Management Process and Medical Device Development

1 year ago
RE: Success Rate of Projects

Thank you for your questions. I agree with others. In my opinion, I believe that a successful project depends on so many factors. Initially, projects have different aims and objectives. If the project...

In forum Project Management Process and Medical Device Development

1 year ago
RE: Key Questions in Root Cause Analysis

Thank you for the question. I agree with others. However, I want to add some more questions which might be useful. what are the conditions at the time of the problem? I think it is important. If prope...

In forum Project Management Process and Medical Device Development

1 year ago
RE: Strategies to Counteract Negative Schedule Variance

It's a good question. I agree with others' answers. First of all, it is important to find out the root cause. In addition, we can further take more steps to Counteract Negative Schedule Variance. We s...

In forum Project Management Process and Medical Device Development

1 year ago
RE: Instances of Multiple PMs

In my opinion, there will be some benefits as well as drawbacks. Benefits 1. Work distribution: multiple PMs can distribute work between them. It will decrease the workload of an individual PM. 2. In...

In forum Project Management Process and Medical Device Development

1 year ago
RE: Compromises in Conflict

In my opinion, Here are some strategies that can be taken to solve this problem. 1. Effective communication Communication is the key. Team members and PMs should listen to others' viewpoints and under...

In forum Project Management Process and Medical Device Development

1 year ago
RE: Risk Management in Medical Device Development

Here, are some steps that we can take to balance between patient safety and innovation. 1. Risk mitigation strategies. To identify risks risk mitigation strategies should be developed. 2. Ethical cons...

In forum Project Management Process and Medical Device Development

1 year ago
RE: Managing a Hectic Workplace

I went through others' comments. I learned so many things. However, I want to give my opinion. In my opinion, a project manager must not have all the knowledge about the project. PM may manage so man...

In forum Project Management Process and Medical Device Development

1 year ago
RE: Planning and Executing in Project Management

Good questions. As a biomedical engineer, I went through different projects. The planning and execution phase is challenging. However, a few steps can be taken in the planning and execution stage for ...

In forum Project Management Process and Medical Device Development

1 year ago
RE: Difficulty of a Project

Good question. I agree with others. However, I would like to add something more. I think experimental design is very difficult. We have to go through different literature and background information. W...

In forum Project Management Process and Medical Device Development

1 year ago
RE: EF and LF in Medical Device Development

Late finish: Example: development of novel approach of vision therapy for convergence insufficiency. Well, this is one of my research projects. In this project, I will develop a novel vision therapy. ...

In forum Project Management Process and Medical Device Development

1 year ago