RE: Organizational structure

In the industry, your company will usually have a defined list of top projects that need to be worked towards by the end of the year and a number of l...

4 years ago
Reply
RE: Discussion Topic: Scope creep....when your project changes

Recently, there was a project I was on that had two instruments removed from scope earlier on in the project as this project was worked on by differen...

4 years ago
Reply
RE: Changining staff

I agree with many who have posted that this does occur more frequently than not on projects. People shift positions or leave a company within the proj...

4 years ago
Reply
RE: Discussion Topic: The proper time for Project Initiation

A project should be initiated once a team has produced a feasible design of a product that can be realistically manufactured and be brought to market ...

4 years ago
Reply
RE: Risk Management impact

Risk is a negative term for many, but it does lead to better innovation for product. There is always a risk assessment completed for a projects I work...

4 years ago
Reply
RE: project Coast

Earnestly, there is no way to budget a project exactly at the beginning. There is too many variables that can change where even when one project that ...

4 years ago
Reply
RE: Meeting Deadlines with Research

I would manage the project team to first see what was completed so far to ensure none of the verification tests have created a sort of issue (whether ...

4 years ago
Reply
RE: Scope Creep

Scope creep can occur due to the indications a system encompasses. If a system is originally chartered for adult patients, but pediatric indications a...

4 years ago
Reply
RE: Design validation

As many have said in this thread, validation of the product confirms the functionality of the product and answers the question on "Does this product w...

4 years ago
Reply
RE: Project failure

A project that fails usually has a poor planning of the prototype with complex features that make lead times on prototypes take way longer than expect...

4 years ago
Reply
RE: Project Plan Execution

I have a couple of years of experience in working with multiple teams (my work place utilizes a matrix type organization where I am usually working 2 ...

4 years ago
Reply
RE: Benefits of this course

For someone that has been in industry for a couple of years, I cannot stress this enough for people to understand the design process and how project m...

4 years ago
Reply
RE: Gantt chart

Going back to this response, a Gantt chart can be used for design verification. At any time of a project, a Gantt chart may be used for a visual aid o...

4 years ago
Reply
RE: Missing Milesons

If the team were to miss a milestone, the project would need to understand the time and resources needed to get to the point that they were aiming for...