Forum

Notifications
Clear all

Personnel evaluation when succeeding project but delaying.

21 Posts
21 Users
0 Reactions
1,327 Views
(@nm234)
Posts: 33
Eminent Member
 

I believe that it is incredibly difficult to be able to identify the positive and negative aspects of delaying a project or even increasing its cost. It is too simplistic of a mindset to think that it is automatically negative to go beyond the initial parameters of the project. Change is all too natural in projects and not being able to accept that change or adapt to it is all the more negative to the project's growth. Though going beyond the parameters should take much consideration and planning. To go beyond the scope of the project should not only act as a reactionary event, but also a way to improve upon the project by considering aspect that was not thought of before. The entire group needs to come to a full agreement on the  position of the project and how to update it. It is then that the person can say that the updates of the project were mainly positive despite it being delayed. 


 
Posted : 29/03/2026 10:23 pm
(@andres-86)
Posts: 66
Trusted Member
 

Delays or increased costs do not automatically mean that a project was unsuccessful, as others have mentioned. Many projects could encounter challenges or delays like supply chain issues, testing complications or changes in requirements that are outside of a team's control (similar to some most here have worked on in school too). Because of this, personnel evaluations should focus not only on whether deadlines or budgets were exceeded, but also on how effectively the team responded to said challenges. If a team member(s) demonstrated strong communication, problem solving skills, and collaboration to deliver a successful product, those should be considered positive aspects that are a boon. Evaluations should also be utilized to include lessons learned (like an after action report) so that future projects can improve planning and risk management while still recognizing the team's accomplishments.


 
Posted : 29/03/2026 11:46 pm
(@jf31634027)
Posts: 36
Eminent Member
 

Since the project was successful, personnel evaluations shouldn't be solely based on delays or increased expenses. Focusing more on the positives than the negatives, roughly 70% positive and 30% negative is a solid way to approach things. Positive aspects include things like problem solving, teamwork, effort, and completing a project successfully. The drawbacks include things like overspends, delays, and problems with planning. However, it's crucial to keep in mind that certain delays like equipment malfunctions or supply delays are unavoidable and beyond the team's control. Delays can occasionally even be beneficial if they enhance quality or avoid more serious issues down the road. This kind of balancing is reasonable since it acknowledges that the team performed well overall while also highlighting areas that could be improved for the future. The most important thing is to learn from the negative aspects and work hard to avoid them moving forward for other projects. With situations like this, people learn from their mistakes and years of experience.


 
Posted : 06/04/2026 10:19 pm
(@cn249)
Posts: 69
Trusted Member
 

In the industry, there is no such thing as a project being 100% successful with no failure, delays, or something going wrong. There also should not be a 100% failure rate on a project with careful planning, organization, and appropriate skills from each team member and project manager. In terms of personnel evaluation, there should be a balance with the positive and negative aspects of the project. They should focus on the positive aspects while taking into consideration the negative aspects, but do not start with blaming each other because that can discourage the team members, making them think the project’s delays are their fault and they should have known or did better. The positives about the project being successful in completion for the market, customer, company goals, and networking should be highlighted indeed and individually.

It should be about 70 to 80% noted at the final team meetings, while 20-30% should highlight the negative aspects of the project like cost increases, resources allocation, and project delay. Most of these projects sometimes focus on the numbers produced by the project itself or if the successful project brought value to the company or not. The positives should highlight what objectives of the project being achieved, any mentions about how the project delay or cost increase was mitigated and handled by different team members or methods. The negative aspects like schedule delays could be due to scope creep and poor deadline planning which can cause bottlenecks. Risk may not have been accounted for. Personnel evaluations should be based on valued success and controlled versus out of control project delays. All of these factors can be listed in the lessons learned section for the current project manager and team members to show what went right, what went wrong, and what could have potentially caused it. This would also help future project managers and team members if they were to work on a similar project and run into the same problem with the project in terms of project delays and increased costs.


 
Posted : 08/04/2026 5:47 pm
(@imarah-ar)
Posts: 61
Trusted Member
 

I think in a situation where a project is ultimately successful but experiences delays or cost increases, the evaluation of personnel should reflect both the positive outcomes and the negative challenges rather than focusing on just one side. The success of the project shows that the team was able to deliver results, which is a major positive, but the delays and cost overruns still matter because they reflect issues in planning, communication, or execution. Because of that, I would lean toward a balanced evaluation, maybe something like a 70/30 or 60/40 split, where the majority of the weight is given to the successful completion of the project, but a meaningful portion still accounts for the setbacks. I think this approach is fair because it recognizes the team’s ability to achieve the end goal while also holding them accountable for areas that could be improved in future projects.


 
Posted : 11/04/2026 6:32 pm
(@jacobchabuel)
Posts: 66
Trusted Member
 

I don't know if I personally can comment on what the ratio of positive and negative aspects are in the instance that a project is successful but faces setbacks. I think at the end of the day, every project is unique and is going to face different issues as development occurs. In some instances delays can be positive for personnel reviews if delays were caused by ensuring regulatory integrity, identifying potential product risks, or ensuring verification requirements are met. Negative reviews could be associated with projects being canceled due to improper resource allocation, or poor documentation processes. The fact that the project is successful is sufficient in itself so long as it is sustainable. And, so long as project personnel did not cause any delays due to negligence, evaluations should not be negative. Depending on the project, individual team members can influence certain project outcomes which may be negative or positive. To further the discussion, how do you think in these instances management should distinguish between justifiable delays and delays due to negligence when conducting personnel reviews?


 
Posted : 12/04/2026 1:25 am
Page 2 / 2
Share: