RE: Changining staff

During my senior design capstone project our sponsor changed the designated project manager multiple times which caused delays throughout our design p...

5 years ago
Reply
RE: Human resource management

Assuming this situation has been anticipated months in advance, I believe the company should consider hiring a temporary or contract employee to fill ...

5 years ago
Reply
RE: Communication Management

Although my team eventually found success in our senior design capstone project, we faced many hurdles throughout the year that were brought on by ina...

5 years ago
Reply
RE: Communication and Responsiveness

I believe it is important to understand how the employee is being unresponsive and what may be causing them to not cooperate. Once this is established...

5 years ago
Reply
RE: Which of the following project would you say is better and why

Assuming the schedule variance and cost variance are both very high values, I would rather have a negative schedule variance and positive cost varianc...

5 years ago
Reply
RE: Most Important Phase

When breaking down a project into the five fundamental project management process groups, I can’t help but designate the executing phase as the most i...

5 years ago
Reply
RE: Design validation

Design validation is important in product development because it provides evidence that the user needs are met. The fundamental purpose of any project...

5 years ago
Reply
RE: Importance of Metrics

Regardless of industry or project size, metrics are essential for successful product development for a number of reasons. Metrics can be used to asses...

5 years ago
Reply
RE: Risk Management impact

My company was recently contracted to perform corrective remediation service on recalled infusion pumps for a well-known manufacturer. This project sp...

5 years ago
Reply
RE: Underestimating Task Duration

My job as a biomedical equipment technician is to work with a team in order to complete work orders for over a dozen different types of medical device...

5 years ago
Reply
RE: Cost Analysis of Project

One of my jobs as a biomedical technician is to maintain inventory so my coworkers and I can provide a consistent stream of work. Depending on the dev...

5 years ago
Reply
RE: Work Breakdown Structure

My only experience with a work breakdown structure was during my senior capstone project as an undergraduate. My group could have certainly developed ...

5 years ago
Reply
RE: Benefits of this course

After graduating with a Bachelor of Science in Biomedical Engineering, I did not feel as prepared for interviews as I do now after taking one of Dr. S...

5 years ago
Reply
RE: Experience Breaking Down A Project

My only experience working in product development was during my senior capstone project as an undergraduate. My team was tasked with developing a test...

5 years ago
Reply
RE: Discussion Topic: What are the PM elements in your company?

I work as a biomedical equipment technician for a company that services medical devices in hospitals throughout the country. My company deals with ext...