Forum

Notifications
Clear all

Monitoring Time and Budget

14 Posts
13 Users
1 Reactions
1,193 Views
(@pv223)
Posts: 76
Trusted Member
Topic starter
 
[#852]

In this week's lecture we learned about different aspects of monitoring and controlling a project and how anything can really be subject to change throughout the life cycle. Assume you are a project manager and you are at about the halfway point of the project. When going over the progress of the project, you notice that the Schedule Variance of the project is negative but not so much that it is irrecoverable, as well as the Cost Variance, meaning that the project is actually behind schedule and you are over the budget for the project. Is it possible to recover this project and finish within expected budgets, and if so, how would you go about it?


 
Posted : 21/03/2022 7:36 pm
(@ridmehta)
Posts: 79
Trusted Member
 

I think it would be possible to recover the project if the remaining tasks can be completed by pooling the most experienced individuals able to complete the tasks with greater efficiency and less resources. That sometimes can also require more money as you are paying individuals for their expertise as well. It may also be beneficial to see if there is another project that is under budget to supplement this one or if any remaining tasks can be shortened (a good PM would have accounted for some leeway in the initial planning process to account for such instances).


 
Posted : 21/03/2022 9:54 pm
 tgt6
(@tgt6)
Posts: 79
Trusted Member
 

While it would be possible to recover this project and finish within expected budgets, it will come at a price. This is the concept of balancing the time and effort versus the cost and whether or not it is worth it to spend the extra money and time for a better final product. Being slightly behind or slightly over budget at the halfway point is not too much of a detriment as long as careful planning and considerations are taken moving forward. There might be extra places to cut costs that may have been previously overlooked or there might have been some unnecessary tasks to perform that will not impact the final product which can be cut out of the timeline. It is important that as the project manager, you are analyzing and seeing why there were these extra costs and delayed progress to begin with and to make sure that this is not happening in the remainder of the project. It is understandable that some of these problems that arise may have been inevitable but it is important that certain acts are taken from letting this problem affect the project further. Overall, it is important to make sure that even though the project may not be going exactly according to plan, it does not mean that the end product will be unsuccessful. 


 
Posted : 22/03/2022 11:39 pm
(@ggmsm22)
Posts: 24
Eminent Member
 

I think it is possible to get the project back on track as long as you have been able to identify what went wrong and why to mitigate the budget and time issues. Having a full scope of the project from that point on may allow for some corrections in areas while making sure your critical success factors are where they need to be. Larger errors can be corrected and fixed but if the project is too far off course you will surely not hit the main success factors that are important to your stakeholders.


 
Posted : 26/03/2022 6:54 pm
(@ac825)
Posts: 55
Trusted Member
 

It could still be possible to finish the project despite the issues with both the schedule and the budget. The fact that we are behind as well as over budget tells me that both time and money are being wasted or the expectations set at the beginning were severely flawed. To fix this the project must be reexamined from the beginning to try and reevaluate the situation and to assess and address the issues that led us to this scenario. Once we can do that we need to refocus the project taking to account what we learned from the first half towards achieving the goal in a more efficient manner.


 
Posted : 27/03/2022 2:33 pm
(@kellyepcarter)
Posts: 33
Eminent Member
 
Posted by: @pv223

In this week's lecture we learned about different aspects of monitoring and controlling a project and how anything can really be subject to change throughout the life cycle. Assume you are a project manager and you are at about the halfway point of the project. When going over the progress of the project, you notice that the Schedule Variance of the project is negative but not so much that it is irrecoverable, as well as the Cost Variance, meaning that the project is actually behind schedule and you are over the budget for the project. Is it possible to recover this project and finish within expected budgets, and if so, how would you go about it?

 


 
Posted : 05/04/2022 3:59 am
(@kellyepcarter)
Posts: 33
Eminent Member
 

I'm one of those people who believes that anything is possible, it boils down to how much work one wants to put in to achieve possible.

I once heard Dolly Parton describe how she and her 11 siblings took baths in a one room house, and she said her mother taught the children, "wash down as far as possible, wash up as far as possible, and when the boys are gone, wash possible, [and vice versa with the boys]."

The way I would attack recovering the project would be to meet with the team, lay out the concerns, and strategize ways to get the project back on schedule. Then task out the work, and monitor the the work very closely.


 
Posted : 05/04/2022 4:05 am
(@crysv1226msm2022)
Posts: 27
Eminent Member
 

I think most things in life are salvageable. In terms of the project management aspect, there are some steps one can take to revamp a failing project.

Refocus the Scope. Begin by going back to the defining documents, including your Charter, Statement of Work, and approved Change Requests, Draw Up the Schedule, Determine the Cost, Review Lessons Learned, Develop Alternatives, Admit Reality and Start Fresh.


 
Posted : 09/04/2022 1:36 pm
(@kaf43)
Posts: 78
Trusted Member
 

Yes, I believe it is possible to recover a project that is behind schedule and over budget. As a project manager the first step to recovering the project would be to find the root cause of the schedule variance and cost variance. A thorough analysis can help pinpoint areas where corrective action is needed. Following the identification of the issues, the next step would be to review both the schedule and the budget to identify areas where the project can be expedited and costs can be reduced. After reviewing the schedule it may be best to prioritize the critical tasks of the project to ensure that the team is working on the most important tasks first. In addition, reassigning resources to the critical tasks will ensure that the right people are working on the right tasks at the right time, overall improving the efficiency of the project. Lastly, communication with the project's stakeholders during all of this is extremely important. Regular communication with stakeholders keeps them informed of the project's progress, risks, and opportunities for improvement. This will help build trust and support for the project, even during a stressful time. Overall these are just a few actions that are necessary to get a project that is behind schedule and over budget back on track, but it is important to remember that recovering a project requires commitment, collaboration, and persistence from the entire project team.


 
Posted : 03/03/2023 4:47 pm
 jj52
(@jj52)
Posts: 75
Estimable Member
 

@ac825 made a great point. If the project is over budget and behind schedule there must be a disconnect amongst the team, improper management, or the initial plan was flawed. There are very seldom times where a project is ran successful without any obstacles along the way. Although the project may be able to salvaged another approach would be requesting and extension on the deadline and an increase in the budget. 

The team may struggle to convince a customer on both but it is important that quality is a factor when making this decision. If a project is rushed or completed with little resources a medical device could be poorly made and put out in the market with potential risks to patients/consumers.


 
Posted : 04/03/2023 1:40 am
 vv48
(@vv48)
Posts: 61
Trusted Member
 

By preparing a contingency plan you are going to identify the problem and understand where the project stands. Once it is figured out, then we can determine the project status. So that we can understand what was done wrong and look for avenues to fix it, so we can be back on track even though we have overbudgeted the project. We might need to prioritize assignments so that way the main points of the project can be satisfied. And eventually, improve our expectations by achieving our goal successfully. 


 
Posted : 11/03/2023 1:15 pm
(@vanshamin)
Posts: 68
Trusted Member
 

While it might be technically possible to recover from being behind schedule and over budget, I think that recovering from both of those conditions is incredibly unlikely. As someone else had said, being a little over budget and a little behind is not too much of an issue that it might kill the project. Most strategies that could let you recover will, as said, come at a cost. Most of that cost will come at some form of assuming additional risk. Compressing the schedule may allow you to complete the same amount of work in less time but comes with the risk of minor delays cascading to catastrophic slowdowns as delays cascade into critical work. Switching to a cheaper supplier may allow you to save some of the budget but comes with the risk of lower quality supplies impacting results or performance, which can incur additional costs and delays. It may be possible to get lucky in every extra risk you take on and to come out of the project on schedule and under budget, or you may just unnecessarily dig the project into an even deeper hole. 


 
Posted : 20/02/2026 3:11 pm
(@nevinantony)
Posts: 76
Trusted Member
 

Yes, it's definitely possible to recover the project, but it's going to require some tough decisions and proactive adjustments. The first thing I'd do is figure out exactly why we're behind schedule and over budget. I'd look at what tasks are taking longer than expected, where we're spending more money than planned, and whether there are any underlying issues like resource constraints, scope creep, or unforeseen complications. Understanding the root cause is critical because you can't fix the problem if you don't know what's causing it.

Once I have a clear picture, I'd reassess the remaining work and look for opportunities to get back on track. One approach is to focus on the critical path identifying which tasks absolutely must be completed on time to finish the project and prioritizing resources there. For non-critical tasks, I might see if we can defer them, reduce their scope slightly, or find more efficient ways to complete them. I'd also look at whether we can fast-track or crash the schedule by overlapping tasks that were originally planned sequentially or by adding resources to critical activities, though I'd be careful because that can sometimes increase costs.

On the budget side, I'd look for areas where we can cut costs without compromising quality or the project's core deliverables. Maybe there are expenses we can trim, vendors we can renegotiate with, or internal resources we can leverage instead of outsourcing. I'd also check if there are any approved changes or scope additions that aren't absolutely necessary and see if stakeholders would be willing to defer those to a later phase. Sometimes just having an honest conversation with stakeholders about trade-offs like reducing certain features or extending the timeline slightly in exchange for staying within budget—can open up options.

Communication is huge here too. I'd keep stakeholders informed about where we stand, what I'm doing to course-correct, and what support or decisions I need from them. If recovering both schedule and budget isn't realistic, I'd present options like finishing on time but needing additional budget, or staying within budget but extending the deadline and let them decide what's most important. The key is being transparent, taking action early before things get worse, and staying focused on delivering the most value possible given the constraints we're working with.


 
Posted : 22/02/2026 8:18 am
(@james-saleh)
Posts: 68
Trusted Member
 

If I were halfway through a project and noticed that both the Schedule Variance (SV) and Cost Variance (CV) were negative, I would first focus on understanding the root cause before reacting. Being behind schedule and over budget does not automatically mean the project is unrecoverable, especially if the variances are still within a manageable range. I would begin by conducting a detailed earned value analysis to determine where the deviations are occurring and whether they are isolated to specific work packages or systemic across the project. Next, I would reevaluate the critical path to identify activities that are driving the delay. For this I might consider fast tracking overlapping tasks or crashing critical activities by reallocating resources while also considering the cost implications of each option. On the cost side, I would examine spending trends and remaining budget forecasts to prevent further overruns. This might involve renegotiating vendor contracts, improving resource allocation efficiency, or tightening cost controls moving forward. I would also have clear and transparent communication with stakeholders. 


 
Posted : 22/02/2026 10:02 pm
Share: