RE: Power of Stakeholders

Stakeholders have very high influence when it comes to shaping a project because projects are done through requirements, funding, and approvals which are all things that stakeholders hold control over...

In forum Project Management Process and Medical Device Development

3 months ago
RE: project changes and stakeholders

First there needs to be an impact analysis on the scope, schedule, cost, and risk to the project. Doing this allows one to ascertain changes to the original project baseline and then one must identify...

In forum Project Management Process and Medical Device Development

4 months ago
RE: Design Transfer

Some of these aspects I had to do during my previous internship as I had to hand off my project to the following intern who would pick up where I left off. Documentation and knowledge transfer is an i...

In forum Project Management Process and Medical Device Development

4 months ago
RE: Lessons Learned

Reporting lessons is valuable in a company/project team as this could help future project teams avoid repeating the same mistakes. It can capture practical knowledge that might not appear in formal pr...

In forum Project Management Process and Medical Device Development

4 months ago
RE: Importance of Stakeholders

In terms of promptness, a manager is far more important. Managers are hands on in control of what happens within a project. Investors provide monetary funds but tend to be mostly hands off. It is not ...

In forum Project Management Process and Medical Device Development

4 months ago
RE: Missing a Milestone Experience

This happens constantly with projects that I am in. Specifically, I'll mention my capstone project. I have limited access to the lab throughout the week, and because of this, I try to utilize my time ...

In forum Project Management Process and Medical Device Development

4 months ago
RE: Ideal PM Processes vs. Real life

I feel like a lot of these phases are followed conceptually, but they could overlap one another or have different areas of importance. Sometimes planning could still continue to be done while executio...

In forum Project Management Process and Medical Device Development

4 months ago
RE: Combination Product

Nicotine gum is a product used by smokers to try to stop or limit smoking. It delivers doses of nicotine through the oral mucosa to help reduce smoking withdrawal symptoms The person is instructed to ...

In forum Project Management Process and Medical Device Development

4 months ago
RE: Things help to understand project status other than project matrix

Three factors that can help detect the status of a project can be as follows: Milestone Completion Rate - This tracks whether milestones are being completed on schedule. This can indicate the project...

In forum Project Management Process and Medical Device Development

4 months ago
RE: how the PM handles budget cut?

I agree with the OP, working under budget may be beneficial in the long run incase of any unforeseen circumstances. However, one must not work so under budget that it affects the quality of the work. ...

In forum Project Management Process and Medical Device Development

4 months ago
RE: Email Communication

As a PM, one can organize their email by using folders and rules to sort through messages, set specific times in the day to respond to messages, and apply priority flags for urgent emails. They also m...

In forum Project Management Process and Medical Device Development

4 months ago
RE: Are Missed Milestones really Bad?

I think it is more important to determine why the milestone was missed. Sometimes milestones are missed due to unforeseen circumstances. This was the case at a previous internship that I was at. There...

In forum Project Management Process and Medical Device Development

4 months ago
RE: Team members personal issues with eachother

First and foremost, I would avoid taking sides and try to remain neutral in these situations. I also believe that it is important to listen to each person by themselves first to get an accurate idea a...

In forum Project Management Process and Medical Device Development

4 months ago
RE: Difference

In short, a project manager is broad and can be a part of any industry. Clinical project managers on the other hand are simply a subset of project managers that are doing healthcare or clinical resear...

In forum Introduction to Project Management

4 months ago
RE: More Influence or Less?

To ensure efficient team member contribution, I would delegate tasks as well as deadlines to each individual as well as daily meetings. I would also offer each member the ability to have open conversa...

In forum Introduction to Project Management

4 months ago